Question: b ) Create an activity table showing the predecessors for the activity based on the AON diagram provided and the updated information given. After much
b Create an activity table showing the predecessors for the activity based on the AON diagram provided
and the updated information given.
After much deliberation the team added and removed the following relationships:
L could start day after the start of J
P does not need N but L as predecessor.
Q as predecessor of P
c Redraw the AON diagram stating the early and latest times for each of the activities using the
information gathered so far. Show proper connections of the arrows and nodes. Consider the SS
relations. Use nonautomated software to draw the diagram such as Visio.
d How long will this project take? What is the completion date?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock