Question: b ) Create an activity table showing the predecessors for the activity based on the AON diagram provided and the updated information given. After much

b) Create an activity table showing the predecessors for the activity based on the AON diagram provided
and the updated information given.
After much deliberation the team added and removed the following relationships:
L could start 1 day after the start of J.
P does not need N but L as predecessor.
Q as predecessor of P.
c) Redraw the AON diagram stating the early and latest times for each of the activities using the
information gathered so far. Show proper connections of the arrows and nodes. Consider the SS
relations. Use non-automated software to draw the diagram such as Visio.
d) How long will this project take? What is the completion date? List all the distinct paths in the project along with their durations. (4 marks)
4
f) Which tasks are on the critical path of the PERT chart above? (2 marks)
g) Identify all Activities in the above project that have a slack and the amount of slack. (4 marks)
h) Draw AON diagram assuming a finish-start (FS) relationship between activities? (5 marks)
i) You are tasked to draw using appropriate software an AOA PERT chart for the above project; assuming
a finish-start (FS) relationship between activities. (The length of the arrows must be indicative of the
duration).(10 marks)
 b) Create an activity table showing the predecessors for the activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!