Question: B D F A H E G Activity Optimistic Time (Weeks) Most Likely Time (weeks) Pessimistic Time (weeks) A 8 10 12 B 4 10

B D F A H E G Activity Optimistic Time (Weeks)

B D F A H E G Activity Optimistic Time (Weeks) Most Likely Time (weeks) Pessimistic Time (weeks) A 8 10 12 B 4 10 16 4 5 6 D 6 8 10 4 7 F 6 7 9 G 4 8 12 H 3 3 3 What is the Expected Project Completion Time for the AON and table above? O 38.17 0 32.5 O 33.33