Question: b . Estimated expected ( mean ) time and standard deviation ( in days ) for project completion c . Probability that the critical path

b. Estimated expected (mean) time and standard deviation (in days) for project completion
c. Probability that the critical path for this project will be completed within 70 days
Given the diagram below:
Find:
(a) The critical path.
(b) How long it will take to complete the project.
(c) Find the ES, LS, EF, and LF for each activity.
(d) Find the slack for each activity.
Given the following network:
(a) What is the critical path?
(b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so,
how many days?
Given the estimated activity times below and the network in Problem 4 above
What is the probability that the project will be completed within (based on the path with the
longest expected time):
(a)21 days?
(b)22 days?
(c)25 days?
Given the following table: Find
(a) The AOA network (draw) and the path with the longest expected duration.
(b) All event slacks.
(c) Critical path to event D.
Find the schedule and cost variances for a project that has an actual cost at month 22 of
$540,000, a scheduled cost of $523,000, and an earned value of $535,000.
A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and
a value completed of $39,000. Find the cost and schedule variances and the CPI and
SPI.Determine the critical path and time for completion.
a. Critical path:
b. Estimated expected time of completion:
Given the following project information:
Determine:
a. Critical path
 b. Estimated expected (mean) time and standard deviation (in days) for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!