Question: You are responsible for developing a supervisory training program for a company. The following table shows the relationships between the activities that must be completed

You are responsible for developing a supervisory training program for a company. The following table shows the relationships between the activities that must be completed and estimates of the durations in days.
Table 3
Required
a. Complete the column labelled \(\mathrm{E}(\mathrm{T})\) in Table 3. Round times to integers (zero decimal places) where fractional.
(2 Marks)
b. Draw the AON activity network that represents the activities and their predecessors, as shown in Table 3.
(3 Marks)
c. Develop a project schedule that shows the earliest and latest start and finish times and activity slack (in a table or in the network diagram).
(6 Marks)
d. Determine and state the critical path for this project.
(2 Marks)
e. What is the expected completion time and standard deviation of the project?
(2 Marks)
You are responsible for developing a supervisory

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!