Question: You are responsible for developing a supervisory training program for a company. The following table shows the relationships between the activities that must be completed
You are responsible for developing a supervisory training program for a company. The following table shows the relationships between the activities that must be completed and estimates of the durations in days.
Table
Required
a Complete the column labelled mathrmEmathrmT in Table Round times to integers zero decimal places where fractional.
Marks
b Draw the AON activity network that represents the activities and their predecessors, as shown in Table
Marks
c Develop a project schedule that shows the earliest and latest start and finish times and activity slack in a table or in the network diagram
Marks
d Determine and state the critical path for this project.
Marks
e What is the expected completion time and standard deviation of the project?
Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock