Question: b . Identify all the paths through the network and their lengths. Fill in the table below ( enter your responses rounded to one decimal

b. Identify all the paths through the network and their lengths. Fill in the table below (enter your responses rounded to one decimal place).
Part 4Part 5Part 6Part 7
Path
Length(days)
A-C-
E-G
14.5
A-
D
-E-G
15
A-
D-F
-G
13.5
B-D
-E-G
13
B-
D-F
-G
11.5
Part 8
c. The critical activities are
so they make up the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!