Question: b. If there are three men available at any one time how long would the project take and how would you allocate the men to

b. If there are three men available at any one time how long would the project take and how would you allocate the men to the activities?
\begin{tabular}{|l|c|c|c|} \hline Job & \begin{tabular}{c} Time \\ (weeks) \end{tabular} & \begin{tabular}{c} No. of Men \\ required \end{tabular} & \begin{tabular}{c} Precedence \\ requirements \end{tabular} \\ \hline A & 5 & 1 & - \\ \hline B & 10 & 1 & A \\ \hline C & 8 & 2 & A,C \\ \hline D & 6 & 3 & B,C \\ \hline E & 7 & 1 & E \\ \hline F & 4 & 2 & D,F \\ \hline G & 4 & 2 & G \\ \hline H & 2 & 1 & \\ \hline \end{tabular}