Question: B. Material Requirement Planning Given below are (i) a master production schedule for an end item A for the next six weeks, (ii) its inventory

B. Material Requirement Planning

Given below are (i) a master production schedule for an end item A for the next six weeks,

(ii) its inventory records file and (iii) its product structure diagram

MPS For Item A

Week >>

1

2

3

4

5

6

Requirements>>

70

50

100

200

250

120

Inventory Records File

Item

Lot-sizing

Scheduled

Inv. on-

Lead

Rule

Receipts

Hand

Time

A

Lot For Lot

50 in Week 2

75

2 weeks

B

EOQ =200

none

200

1 week

C

POQ = 2 weeks

500 in Week 1

700

1 week

D

EOQ =300

800 in Week 1

700

1 week

Develop the MRP tables for items A, B, and C using the lot-sizing rules indicated in the table above.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!