Question: B. Material Requirement Planning Given below are (i) a master production schedule for an end item A for the next six weeks, (ii) its inventory
B. Material Requirement Planning
Given below are (i) a master production schedule for an end item A for the next six weeks,
(ii) its inventory records file and (iii) its product structure diagram
| MPS For Item A
| ||||||
| Week >> | 1 | 2 | 3 | 4 | 5 | 6 |
| Requirements>> | 70 | 50 | 100 | 200 | 250 | 120 |
| Inventory Records File | |||||
| Item | Lot-sizing | Scheduled | Inv. on- | Lead | |
| Rule | Receipts | Hand | Time | ||
|
|
| 50 in Week 2 | 75 | 2 weeks | |
| B | EOQ =200 | none | 200 | 1 week | |
| C | POQ = 2 weeks | 500 in Week 1 | 700 | 1 week | |
| D | EOQ =300 | 800 in Week 1 | 700 | 1 week | |
Develop the MRP tables for items A, B, and C using the lot-sizing rules indicated in the table above.