Question: Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance of each activity and state and interpret the

Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance of each activity and state and interpret the standard deviation of the overall project.

*PLEASE SHOW ALL CALCULATIONS*

Activity

Predecessors

Optimistic (a)

Most Likely (m)

Pessimistic (b)

A

-

2

3

4

B

-

3

4

5

C

B

3

5

6

D

A

2

2

2

E

D

1

4

5

F

D

2

3

4

G

C,F

1

3

5

H

E,G

3

5

6

Step by Step Solution

3.38 Rating (148 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!