Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance of each activity and state and interpret the standard deviation of the overall project.
*PLEASE SHOW ALL CALCULATIONS*
Activity | Predecessors | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
A | - | 2 | 3 | 4 |
B | - | 3 | 4 | 5 |
C | B | 3 | 5 | 6 |
D | A | 2 | 2 | 2 |
E | D | 1 | 4 | 5 |
F | D | 2 | 3 | 4 |
G | C,F | 1 | 3 | 5 |
H | E,G | 3 | 5 | 6 |