Question: B- What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how they are listed?
B- What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how they are listed?
| Job | Processing Time | Days Due from Today |
| A | 16 | 24 |
| B | 20 | 16 |
| C | 22 | 40 |
| D | 12 | 17 |
| E | 10 | 18 |
options:
| Average flowtime would decrease by 12.6 | |
| Average flowtime would decrease by 10.0 | |
| Average flowtime would decrease by 13.8 | |
| Average flowtime would decrease by 10.6 | |
| Average flowtime would decrease by 6.4 |