Question: Question 27 (3.03 points) What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how
Question 27 (3.03 points)
What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how they are listed?
| Job | Processing Time | Days Due from Today |
| A | 20 | 24 |
| B | 23 | 15 |
| C | 22 | 40 |
| D | 14 | 28 |
| E | 10 | 16 |
Question 27 options:
|
| Average flowtime would decrease by 10.6 |
|
| Average flowtime would decrease by 12.6 |
|
| Average flowtime would decrease by 10.0 |
|
| Average flowtime would decrease by 6.4 |
|
| Average flowtime would decrease by 13.8 |
Question 28 (3.03 points)
If four workers (1 assigned to each task) are assigned to the following Four Task Assembly Line, which task will have a lack of work delay?
Question 28 options:
|
| Task A |
|
| Task B |
|
| Task C |
|
| None of these |
Question 29 (3.03 points)
If four workers (1 assigned to each task) are assigned to the following Four Task Assembly Line, which task will have a lack of work delay?
Question 29 options:
|
| Task A |
|
| Task B |
|
| Task C |
|
| None of these |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
