Question: What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how they are listed? Job
What would be the difference in Average Flowtime if you did the following jobs by Shortest Processing Time instead of how they are listed?
Job Processing Time Days Due from Today A 16 22 B 21 30 C 22 36 D 14 28 E 10 18 Question 3 options:
Average flowtime would decrease by 6.4
Average flowtime would decrease by 10.6
Average flowtime would decrease by 10.0
Average flowtime would decrease by 13.8
Average flowtime would decrease by 12.6