Question: b. Write the critical path and calculate the expected duration and standard variance of the critical path. d. Draw the Gantt Chart for this problem.

b. Write the critical path and calculate the expected duration and standard variance of the critical path.
d. Draw the Gantt Chart for this problem.
Consider the network described in the table below. Activity J K Immediate Predecessor(s)Pessimistic (b) Probable (m) Optimistica) 16 10 8 10 8 7 11 6 5 4 3 3 . 10 5 KM 11 4 L.N 11 8 3 J ZKF J mlin 0 P a. Draw the network diagram and fill out the chart below (by doing the forward and backward path analysis)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
