Question: Bailey Builders Corporation accepted a three-year, $1,000,000 fixed-fee contract to renovate a parking deck. Bailey uses the completed contract method of measuring progress. Information related

Bailey Builders Corporation accepted a three-year, $1,000,000 fixed-fee contract to renovate a parking deck. Bailey uses the completed contract method of measuring progress. Information related to the construction contract is presented below.

Bailey Builders Corporation accepted a three-year, $1,000,000 fixed-fee contract to renovate aDescription

Reading order description of t-table

Contract price $1,000,000
2015 2016 2017
Actual construction costs incurred during the year $350,000 $525,000 $ 50,000
Construction costs incurred in prior years 0 350,000 875,000
Cumulative construction costs incurred to date $350,000 $875,000 $925,000
Estimated costs to complete 450,000 25,000 0
Estimated total costs $800,000 $900,000 $925,000
Progress billings made during the year $500,000 $300,000 $200,000
Cash collections during the year 400,000 $350,000 $250,000

Prepare the journal entries required in each year to record the contract. Show all supporting computations.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!