Question: Based on historical weather data, a particular project is expected to be impacted by six adverse weather days. Using one of the procedures described in
Based on historical weather data, a particular project is expected to be impacted by six adverse weather days. Using one of the procedures described in this chapter, make the appropriate allowance for adverse weather and solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.