Question: Based on Microsoft project program answer Which of the following settings under the Resource Leveling dialog box allows Microsoft Project the ability to delay a

Based on Microsoft project program answer

Based on Microsoft project program answer Which

Which of the following settings under the Resource Leveling dialog box allows Microsoft Project the ability to delay a task without affecting the other resources working on the same task? Level manually scheduled tasks Leveling can create splits in remaining work Level only within available slack Leveling can adjust individual assignments to work on a task