Question: Based on the activity time estimates, the expected times and variance for each of the activities are ( round your response to two decimal places

Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):
Part 3Part 4Part 5
Activity
Expected Time
Variance
A
10.33
.44
B
11.50
3.36
C
9.83
.69
D
8.00
1.78
Part 6
b) The expected completion time of the critical path=
31.67 weeks (round your response to two