Question: Based on the below information: - Planned value (PV) =$2,200, - % Work completed =24%, - Actual Cost (AC)=$2,500, - Budget at completion (BAC)=$10,000 The

 Based on the below information: - Planned value (PV) =$2,200, -

Based on the below information: - Planned value (PV) =$2,200, - % Work completed =24%, - Actual Cost (AC)=$2,500, - Budget at completion (BAC)=$10,000 The cost variance (CV) for this project is: $200$100$100$200