Question: Based on the below project details, Develop the project Network diagram (10 marks), Identify the Critical Path(s) and the Expected Total duration of the project
Based on the below project details,
- Develop the project Network diagram (10 marks),
- Identify the Critical Path(s) and the Expected Total duration of the project (5 marks)
- Find each activitys ES, EF, LS, LF and Slack and identify which activities has free slack (5 marks)
| ID | Predecessor | Time |
| A | NONE | 4 |
| B | NONE | 6 |
| C | NONE | 4 |
| D | A,C | 2 |
| E | A,B | 4 |
| F | D,E | 5 |
| G | D | 3 |
| H | B,F | 4 |
| I | D,F | 2 |