Question: Question 2: Based on the below project details, Develop the project Network diagram (10 marks), Identify the Critical Path(s) and the Expected Total duration of
Question 2: Based on the below project details,
- Develop the project Network diagram (10 marks),
- Identify the Critical Path(s) and the Expected Total duration of the project (5 marks)
- Find each activitys ES, EF, LS, LF and Slack and identify which activities has free slack (5 mark)
ACTIVITY. DURATION(DAYS) PREDECESSOR
A 4 none
B 6 none
C 4 none
D 2 a,c
E 4 a,b
F 5 d,e
G 3 d
H 4 b.f
I 2 d,f
Can you please postl the answer in a word document .