Question: 2Based on the below project details ( ) Develop the project Network diagram (10 marks) Identify the Path(s) and the Expected Total duration of the
2Based on the below project details ( ) Develop the project Network diagram (10 marks) Identify the Path(s) and the Expected Total duration of the project (5 marks) Fird each activity's ES EF, LS, LF and Slack and identify which activities free Duration (Days) Activity a 4 b 6 4 d 2 Predecessor none none none a, c; a, b; d, e d b, f; d, f 4 5 3 4 2