Question: Based on the following table, and using the PERT technique answer the next questions. Activity A B D E F G H I a 4

Based on the following table, and using the PERT

Based on the following table, and using the PERT

Based on the following table, and using the PERT technique answer the next questions. Activity A B D E F G H I a 4 2 6 10 4 5 3 7 8 The value of for activity D is _____. 11 12 15 18 m 6 4 6 12 7 8 5 9 10 b 10 6 7 12 8 10 7 12 14 The value of 5^2 for activity I is_____ .30 .45 .55 O 1.00 5 puntos The Critical Path of the project using is. A, C, F, H A, A, B, C, F, H A, B, C, F, H, I B, F, H 5 puntos The probability of finish the project in 30 days or less is ____. 57% 62% 70% 74%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!