Question: This is the only information provided in the test Based on the following table, and using the PERT technique answer the next questions. Activity A


This is the only information provided in the test
Based on the following table, and using the PERT technique answer the next questions. Activity A B D E F G H I a 4 2 6 10 4 5 3 7 8 m 6 4 6 12 7 8 5 9 10 b 10 6 7 12 8 10 7 12 14 The probability of finish the project in 30 days or less is _____. O 57% O 62% O 70% O 74% Based on the following table, and using the PERT technique answer the next questions. Activity A B D E F G H I a 4 2 6 10 4 5 3 7 8 m 6 4 6 12 7 8 5 9 10 b 10 6 7 12 8 10 7 12 14 The probability of finish the project in 30 days or less is _____. O 57% O 62% O 70% O 74%Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock