Question: Based on the information given below, calculate availability, performance, quality, and OEE Planned run time : 18 hours Set up time : 2 hour Breakdowns
- Based on the information given below, calculate availability, performance, quality, and OEE
Planned run time : 18 hours
Set up time : 2 hour
Breakdowns : hour
Theoretical rate/hr : 150
Theoretical production : 5000 units
Actual production : 4500 units
Quality rework : 120
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts