Question: Based on the network diagram and resource schedule below, using the parallel method heuristic and assuming only 3 resources are available, determine the period in
Based on the network diagram and resource schedule below, using the parallel method heuristic and assuming only resources are available, determine the period in which the overall project will actually be completed.
ES resource load chart
tableIDRES,DUR,ESLFSLtableotal resourd,e lood,,PP