Question: Based on the Precedence Table below, what is the Critical Path of this project? Task Precedent Duration A None 2 B A 4 C A

Based on the Precedence Table below, what is the Critical Path of this project? Task Precedent Duration A None 2 B A 4 C A & B D C 6 E None 5 F A G C, E & F 2 O A, B, C and D O E, F and G O E and G O A, F and G O A, B, CG