Question: Exercise 2: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and
Exercise 2: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and show the critical path for the project. Task (T) Duration (days) Dependencies Plan course 5 Instructional design 4 Plan course (M1) Story boarding 4 Plan course (M2) Graphics 6 Story boarding Simulation 10 Instructional Design (M3), Graphics (M4) Integration 6 Simulation Review 2 Integration Testing 8 Integration (M5) Release 1 Testing
can you solve it please
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts