Question: Exercise 2: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and

Exercise 2: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and show the critical path for the project. Task (T) Duration (days) Dependencies Plan course 5 Instructional design 4 Plan course (M1) Story boarding 4 Plan course (M2) Graphics 6 Story boarding Simulation 10 Instructional Design (M3), Graphics (M4) Integration 6 Simulation Review 2 Integration Testing 8 Integration (M5) Release 1 Testing

can you solve it please

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!