Question: Based on the table below, draw a project network from the following information: What activity ( s ) is a burst activity? What activity (
Based on the table below, draw a project network from the following information: What activitys is a burst activity? What activitys is a merge activity? What is the critical path?
Work Packages
ID Description Predecessor Durations
A Survey Site None Days
B Excavate Site A Days
C Install Power Lines B Days
D Install Drainage B Days
E Pour Foundation C D Days