Question: Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity?

 Based on the table below, draw a project network from the

following information: What activity(s) is a burst activity? What activity(s) is a

Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path? Work Packages ID Description Predecessor A Survey Site None B Excavate Site A C Install Power Lines B K D Install Drainage B E Pour Foundation C, D