Based on the tables given below, answer the questions that follow.

Risk Probable Impact (in $ Million) Probable Velocity

Non-Financial Impact

Risk 1: Data hacking, which could lead to a breach and loss of data

1.7 to 1.9 million

High

Loss of data security

Risk 2: Use of old technology saws, which leads to 15% raw material wastage 3.1 to 3.4 million Low Probable loss of employee branding
Risk 3: Pandemic induced market depression, which could lead to reduced sales 4.5 to 4.7 million Medium Loss in motivation for the sales team

Risk 4: New regulations on working shifts that could lead to shutting down of night shift working in factories

2.4 to 2.6 million High Lay-offs of night shift workers
Risk 5: End customers preferring biodegradable plastic packaging, which might impact the current product line 0.6 to 0.8 million Low No growth in brand value
Impact Scale Probable Impact (in $ Million)
1 0-0.9 million
2 1.0-1.9 million
3 2.0-2.9 million
4 3.0-3.9 million
5 4.0 million and above

Question :Suppose Stora Ensos risk tolerance for each of the risks mentioned in the table is $3 million (the amount that it is willing to lose in the event the project does not work out). What risks would you suggest Stora Enso should take?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!