Question: begin{tabular}{ccc} hline Activity & Activity Time (days) & Immediate Predecessor(s) hline A & 2 & B & 3 & C & 4

\begin{tabular}{ccc} \hline Activity & Activity\begin{tabular}{ccc} \hline Activity & Activity

\begin{tabular}{ccc} \hline Activity & Activity Time (days) & Immediate Predecessor(s) \\ \hline A & 2 & \\ B & 3 & \\ C & 4 & \\ D & 3 & \\ E & 7 & A \\ F & 4 & B, C, D \\ G & 4 & E, F \\ H & 3 & F \\ I & 4 & G \\ J & 3 & G \\ K & 4 & H \\ \hline \end{tabular} a. Choose the correct network diagram for this project. The critical path is path