Question: begin{tabular}{ccc} hline Activity & Activity Time (weeks) & Immediate Predecessor(s) hline A & 2 & - B & 10 & - C


\begin{tabular}{ccc} \hline Activity & Activity Time (weeks) & Immediate Predecessor(s) \\ \hline A & 2 & - \\ B & 10 & - \\ C & 7 & A \\ D & 12 & B, C \\ E & 9 & B \\ F & 4 & D \\ G & 6 & E \\ H & 6 & F, G \end{tabular} a. Choose the correct network diagram below A. B. C D. b. Calculate the slack for each activity Which activities are on the critical path