Question: begin{tabular}{ccc} hline Activity & Duration (days) & Predecessors hline A & 6 & None B & 4.5 & None C & 7.5


\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 6 & None \\ B & 4.5 & None \\ C & 7.5 & A \\ D & 2 & A, B \\ E & 7 & C, D \\ F & 5 & D \\ G & 7 & E, F \\ \hline \end{tabular} Consider the following project activities. Click the icon to view the project activities. a. Choose the correct project network diagram below. c