Question: begin{tabular}{ccc} hline Activity & Duration (days) & Predecessors hline A & 3.5 & None B & 3 & None C & 7.5


\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 3.5 & None \\ B & 3 & None \\ C & 7.5 & None \\ D & 5.5 & A,B \\ E & 6.5 & C \\ F & 5 & D, E \\ G & 2.5 & F \\ H & 5.5 & F \\ \hline \end{tabular} a. Choose the correct project network diagram below A. c. D