Question: begin{tabular}{|l|l|} hline Path & Duration hline ABEF & 9 days hline ACF & 6 days hline ADF & 8 days hline

\begin{tabular}{|l|l|} \hline Path & Duration \\
\begin{tabular}{|l|l|} \hline Path & Duration \\
\begin{tabular}{|l|l|} \hline Path & Duration \\ \hline ABEF & 9 days \\ \hline ACF & 6 days \\ \hline ADF & 8 days \\ \hline \end{tabular} According to the Project Cash information above, what is the total cost to complete this project in 7 days if crashed in the most cost-efficient manner? $180 $220 $240 $270