Question: begin{tabular}{|l|r|r|r|r|} hline Task & Normal Task Time & Time When Fully Crashed Cost to Fully Crash Critcal Path hline A & 9 & 6
\begin{tabular}{|l|r|r|r|r|} \hline Task & Normal Task Time & Time When Fully Crashed Cost to Fully Crash Critcal Path \\ \hline A & 9 & 6 & $2,349.90 & No \\ \hline B & 11 & 10 & $1,137 & Yes \\ C & 5 & 3 & $800 & No \\ \hline D & 7 & 4 & $1,700.50 & Yes \\ E & 5 & 1 & $1,826.20 & No \\ \hline F & 8 & 6 & $2,183.60 & Yes \\ G & 9 & 8 & $1,490.60 & Yes \\ H & 10 & 9 & $251 & No \\ \hline What task should you crash ? & & & & \\ \hline SHOW ALL MATH & & & \end{tabular}