Question: Task Normal Task Time Time When Fully Crashed Cost to Fully Crash Critcal Path A 9 6 $2,349.90 No B 11 10 $1,137 Yes C

Task Normal Task Time Time When Fully Crashed Cost to Fully Crash Critcal Path A 9 6 $2,349.90 No B 11 10 $1,137 Yes C 5 3 $800 No D 7 4 $1,700.50 Yes E 5 1 $1,826.20 No F 8 6 $2,183.60 Yes G 9 8 $1,490.60 Yes H 10 9 $251 No What task should you crash