Question: Below are data for a project Activity Predecessors Normal Time (weeks) Maximum Crash (weeks) Crash Cost per week a - 9 3 $500 b a

Below are data for a project

Activity

Predecessors

Normal Time (weeks)

Maximum Crash (weeks)

Crash Cost

per week

a

-

9

3

$500

b

a

7

1

$400

c

a

4

2

$200

d

b

2

5

$300

e

c

7

4

$600

f

d and e

5

4

$400

Determine how much to crash each activity so as to complete the project in 21 weeks at minimum cost. You may use either linear programming or hand calculation