Question: Below are data for a project Activity Predecessors Normal Time (weeks) Maximum Crash (weeks) Crash Cost per week a - 9 3 $500 b a
Below are data for a project
| Activity | Predecessors | Normal Time (weeks) | Maximum Crash (weeks) | Crash Cost per week |
| a | - | 9 | 3 | $500 |
| b | a | 7 | 1 | $400 |
| c | a | 4 | 2 | $200 |
| d | b | 2 | 5 | $300 |
| e | c | 7 | 4 | $600 |
| f | d and e | 5 | 4 | $400 |
Determine how much to crash each activity so as to complete the project in 21 weeks at minimum cost. You may use either linear programming or hand calculation