Question: Below is a p chart for a process. Based on this chart, is the process statistically stable? UCI 09 0.7 0.6 0.5 04 0.3 0.2

Below is a p chart for a process. Based on this chart, is the process statistically stable? UCI 09 0.7 0.6 0.5 04 0.3 0.2 0.1 LOL 5 10 15 20 25 30 35 401 145 55 60 OYes, it appears to be statistically stable. No, for more than one of the reasons listed below in the answer choices. ONo, there is an obviously non-random trend, cycle, or pattern. No, at least one point is more extreme than the upper or lower control limits. O No, at least 8 consecutive points are located all above or below the centerline. No, because there are at least 6 consecutive points that alternate between up and down
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts