Question: Below is a table that contains various information about the different activities of our project. We need to know the critical path and the total

Below is a table that contains various information about the different activities of our project. We need to know the critical path and the total time of the project, i.e. the time of the critical path. Please click on the activity letters for the critical path and type in the total time rounded to the nearest hour.

Activity Name Predecessor Activity Est. Hours to Complete Activity
A --- 16
B A 13
C A B 12
D A 5
E D 12
F C 9
G D 3
H A D F 14
J E 14
K F 18
L E G H J 20
M A C E G H K 20
N J M 16
P B L M 5
Q G L 11
R D L Q 8
S N P Q R 13

Check the boxes next to the activities along the critical path:

A B C D E
F G H J K
L M N P Q
R S

Type in the total time for the critical path _____

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!