Question: Below is an activity network with times ( in weeks ) shown above each node: The network branching is as follows. A 5 weeks, to
Below is an activity network with times in weeks shown above each node:
The network branching is as follows. A weeks, to B weeks and C weeks. B branching to D weeks and E weeks. D and E to F weeks. C and E to G weeks. F and G to H weeks.
What is the earliest start time for Activity G
Multiple Choice
weeks
weeks
weeks
weeks