Question: Below is an activity network with times ( in weeks ) shown above each node: The network branching is as follows. A 5 weeks, to

Below is an activity network with times (in weeks) shown above each node:
The network branching is as follows. A 5 weeks, to B 7 weeks and C 7 weeks. B branching to D 6 weeks and E 3 weeks. D and E to F 4 weeks. C and E to G 8 weeks. F and G to H 5 weeks.
What is the earliest start time for Activity G?
Multiple Choice
15 weeks
18 weeks
23 weeks
28 weeks