Question: Below is an activity network with times (in weeks) shown above each node: What is the latest start time for Activity H? Multiple Choice 24

 Below is an activity network with times (in weeks) shown above

Below is an activity network with times (in weeks) shown above each node: What is the latest start time for Activity H? Multiple Choice 24 weeks 23 weeks 19 weeks 28 weeks