Question: Below is an activity network with times (in weeks) shown above each node: The network branching is as follows. A 5 weeks, to B 7

Below is an activity network with times (in weeks) shown above each node: The network branching is as follows. A 5 weeks, to B 7 weeks and C 7 weeks. B branching to D 6 weeks and E 3 weeks. D and E to F 4 weeks. C and E to G 8 weeks. F and G to H 5 weeks. What is the slack time for Activity G? Multiple Choice 0 week 2 weeks 1 week 4 weeks