Question: Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates ( in days ) for each activity. However, we just

Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates (in days) for each activity. However, we just found out that a mistake was made and that activity 4-6 should have the following values associated with it: 1-6-16. Use this information and the diagram to answer the question below. What is the expected duration of the project?
I have an answer but I'm not sure it's correct. I want to verify it.3. Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates (in days) for each activity. However, we just found out that a mistake was made and that activity \(4-6\) should have the following values associated with it: 1-6-16. Use this information and the diagram to answer the question below.
A. What is the expected duration of the project? Be sure you use the following weighting:
\[
\frac{T_{0}+4 T_{I}+T_{P}}{6}
\]
Expected duration: 20
Below is an AOA diagram that includes the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!