Question: Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates ( in days ) for each activity. However, we just
Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates in days for each activity. However, we just found out that a mistake was made and that activity should have the following values associated with it: Use this information and the diagram to answer the question below. What is the expected duration of the project?
I have an answer but Im not sure it's correct. I want to verify it Below is an AOA diagram that includes the optimistic, most likely, and pessimistic time estimates in days for each activity. However, we just found out that a mistake was made and that activity should have the following values associated with it: Use this information and the diagram to answer the question below.
A What is the expected duration of the project? Be sure you use the following weighting:
fracT TITP
Expected duration:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
