Question: Below is the project data for a Time-Cost CPM scheduling model. Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost $200 $400 $300
Below is the project data for a Time-Cost CPM scheduling model. Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost $200 $400 $300 $600 $200 $200 $500 $550 $500 $900 A BCDE None A A B and C D NN 2 4 2 3 3 1 3 1 2 2 What is the critical path? What is the total project duration? If you had to reduce the project duration by 1, which activity would you crash?
Step by Step Solution
There are 3 Steps involved in it
Answer To determine the critical path and total project duration we need to calculate th... View full answer
Get step-by-step solutions from verified subject matter experts
