Question: Bods construction is working on kitchen remodeling project. Information about the project is provided in the table below. You are assigned to: a. Draw AON

Bods construction is working on kitchen remodeling project. Information about the project is provided in the table below. You are assigned to: a. Draw AON diagram with ES, EF, LS, LF, and slack time. b. Determine the probability of completing project in 23 days c. Determine the probability of completing project in 25 days Activity Most Likely Pessimistic (b) Immediate Predecessor - - A Optimistic (a) 3 12 2 B 8 15 6 9 19 18 16 20 7 B.D