Question: Could you please help me with question 2.1 and 2.2. Thank you! You are the project manager assigned to a project. Use the information given

Could you please help me with question 2.1 and

Could you please help me with question 2.1 and 2.2. Thank you!

You are the project manager assigned to a project. Use the information given and complete the CPM calculations. 2.1 Develop a network diagram. (5) 2.2 Use the table provided to formulate your answer. (15) Activity Duration in days 2 3 Preceding activity Start A A B C D F A B D E F 1 5 3 3 Table to use for Question 2.2 ES EF LS LF Float Activity A B D E F Duration 2 3 1