Question: Boeing wants to develop a precedence diagram for an electrostatic wing component that requires a total assembly time of 66 minutes. b. Boeing determines that

Boeing wants to develop a precedence diagram for an electrostatic wing component that requires a total assembly time of 66 minutes. b. Boeing determines that there are 480 productive minutes of work available per day. Furthermore, the production schedule requires that 40 units of the wing component be completed as output from the assembly line each day. It now wants to group the tasks into workstations