Question: Both PERT, Program Evaluation and Review Technique, and CPM , Critical Path Method, are widely used techniques for planning and coordination large projects. By using

Both PERT, Program Evaluation and Review Technique, and CPM, Critical Path Method, are widely used techniques for planning and coordination large projects. By using PERT and/or CPM Project Managers are able to obtain;
a. Graphical displays of project activities
b. Estimates of how long the project will take
c. Indication of which activities are the most critical to timely project completion
d. Indication of how long any activity can be delayed without delaying the project
e. All of the above
 Both PERT, Program Evaluation and Review Technique, and CPM, Critical Path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!