Question: PERT ( Program Evaluation and Review Technique ) and CPM ( Critical Path Method ) are very similar approaches to project management. The main difference

PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are very similar approaches to project management. The main difference is that CPM only uses one time factor per activity while PERT employs three time estimates for each activity. The three time estimates in PERT allow you to calculate the probability of completing a project by a due date.